November 12, 2026
"The catalyst of this project was essentially this roundabout here at the westbound (I-70) off-ramp," Courtney Meade, a lead roadway engineer with design firm WSP USA, told a crowd at the Frisco Day Lodge in October 2023. Summit Daily reported her full explanation. "The existing roundabout essentially breaks down. If you can picture all the northbound traffic on Highway 9, there are so many cars coming through it to make that westbound on I-70. There's no gaps in the traffic."
Keep that roundabout in mind when you drive the interchange this winter. The Colorado Department of Transportation shut down construction on Friday, Oct. 30, after a first season that started in spring 2026. The fresh concrete and wide new bridge deck you cross on Highway 9 are finished. CDOT plans to replace the roundabout Meade described with a signalized intersection in 2027. Until crews come back in April, Exit 203 is a half-built interchange. The Highway 9 side has been rebuilt, and the fix for the westbound off-ramp roundabout, the original reason for the project, is still on next season's list.
CDOT and its prime contractor, Zak Dirt, spent the first season on Highway 9. The big milestone was a new underpass bridge and a full-width bridge deck, which carries two lanes in each direction. CDOT says that lets all Highway 9 lanes stay open through the winter. In the CDOT winter shutdown announcement, Executive Director Shoshana Lew said the agency was proud of "having two lanes of travel fully open in both directions on Highway 9 in time for ski season."
Most of the rest of the first season's work is out of sight, and almost all of it sets up season two:
| Completed or advanced in 2026 | What it sets up |
|---|---|
| New underpass bridge and full-width Highway 9 deck | Two lanes each way through winter, and the future crossing for cyclists and pedestrians |
| All Exit 203 on- and off-ramps widened | Room for lane changes during the 2027 work |
| Foundation built for a wider I-70 bridge | The bridge widening planned for 2027 |
| Retaining walls | Stable slopes beside the roadway |
| Stormwater and sanitary sewer line improvements | Drainage for the new layout |
| Stormwater detention pond near Dillon Dam Road | Runoff control on the Dillon Dam Road side |
The town's April notice set the goals for that season: keep two lanes open in the daytime, avoid full closures, and hold Highway 9 and I-70 lane closures to nighttime hours, apart from a short daytime sewer detour on Dillon Dam Road. That's why the summer felt like a run of traffic shifts and never a shutdown. It also explains the order of the work: CDOT rebuilt Highway 9 first so it could carry full traffic while everything else is reworked around it.
The trouble at Exit 203 has always shown up on I-70. Meade's explanation, as Summit Daily reported it, is that the steady stream of northbound Highway 9 drivers heading for westbound I-70 leaves no gaps at the off-ramp roundabout. Cars leaving the interstate end up stopped on the ramp, and drivers behind them have to brake from the 70 mph limit sooner than they expect.
In December 2025, Summit Daily described a dash-camera recording of a car waiting to exit that was hit by a vehicle that didn't slow down in time. The car rolled off the highway, and no one was hurt. The same story cited a meeting memo saying today's queues alone didn't necessarily call for a change, but the traffic projections did. Those forecasts go back to a 2019 CDOT study. According to a Town of Frisco council recap, it modeled the interchange through 2045 and projected a level of service F, a grade the study called unacceptable.
CDOT's own list of 2027 work makes the same point. It says the coming changes are meant to improve safety and traffic flow "particularly for vehicles traveling from the westbound I-70 off-ramp onto southbound CO 9." Replacing the existing interchange roundabout with a signal is on that list, so the main fix is still ahead. The 2026 work did widen all the on- and off-ramps, but CDOT describes that as room for the lane changes needed during season two.
The second season moves the work from Highway 9 to the roads beside it. Here's the sequence as CDOT and Summit Daily's October 26 report describe it:
When the town walked through this design in 2024, it said the layout avoids left turns, adds capacity and removes the Lusher Court and Dillon Dam Road signal. So the underpass you've been driving over all fall will become a road and path crossing beneath Highway 9 next year. The project stays on track to finish in October 2027, and CDOT lists the construction cost at $27.1 million.
For most of Frisco, Lusher Court is where the interchange shows up in daily life, because next season's construction will surround the businesses there. Whole Foods Market sits at 261 Lusher Court. Outer Range Brewing runs its taproom at 182 Lusher Court, and Mountain Dweller Coffee operates inside it at the same address. Epic Mountain Gear's Frisco store is at 223 Lusher Court.
All of these are reached today through the Lusher Court and Dillon Dam Road signal, and that signal is scheduled to be removed. Once the project is done, the route to them changes from a signal to the frontage road and its roundabouts. Over the 2027 season, getting to these addresses will run through active construction. The project page lists daytime work Monday through Saturday from 7 a.m. to 7 p.m., occasional Sundays as needed, and planned night shifts from 7 p.m. to 7 a.m. for barrier placement, striping and sewer work. This winter is the last stretch of steady access before that work begins.
The state builds the roads, and Frisco handles how the area around them looks. At its Oct. 27 meeting, the Frisco Town Council adopted a $3,083,550 capital program for 2027. It includes landscape design for Exit 203 and sidewalk and landscape design for Highway 9, alongside Marina Park restrooms, snowmaking at the Frisco Adventure Park, and path and sidewalk work, according to the town's council recap.
The town's landscape design for the interchange is in its 2027 program, the same year CDOT is scheduled to build the frontage road, the two new roundabouts at its ends, and the paths. The multiuse paths across I-70 are where the project reaches beyond drivers. CDOT's project page says the work adds new bicycle and pedestrian connections across both Highway 9 and I-70.
CDOT's Exit 203 project page has project maps and a video simulation of the finished interchange. It's the quickest way to see where the frontage road and its two roundabouts will sit relative to the stores on Lusher Court. For day-to-day road conditions, CDOT points drivers to COTrip.org. The project team takes questions at 970-817-8647 or [email protected]. Construction is scheduled to resume in April 2027.
Roadwork near a property shapes how guests arrive, how owners plan check-ins, and what buyers ask about during a showing. At Majestic Lodging & Real Estate Company, we manage homes and help people buy and sell all over Frisco, so we keep a close eye on the Exit 203 schedule. If you own near Lusher Court or Dillon Dam Road and want to plan around the 2027 season, Let's Connect.
Stay up to date on the latest real estate trends.
With years of experience and hands-on insight into the local market, Ryan provides tailored strategies to maximize value and simplify every step of the property journey.